|
The remains of Stevenson's breakwater
Image by NSI
|
Wick breakwaterSignificance: In the mid 19th century, Thomas Stevenson attempted to build a breakwater for the harbour at Wick. Despite its robust construction, the breakwater was never completed due to storm damage. Its loss provided perhaps the first clear demonstration of the power of waves to move large blocks of rock.
Several attempts were made to construct a breakwater in Wick Bay between 1863 and 1873. The end of the breakwater was capped by an 726 tonne block of concrete that was secured to the foundation by iron rods 9 cm in diameter. In a storm in 1872 Stevenson watched in amazement from a nearby cliff as both cap and foundation, weighing a total of 1225 tons, were removed as a unit and deposited in the water that the wall was supposed to protect. He rebuilt the structure and added a larger cap weighing 2358 tons, which was treated similarly by a storm a few years later.
|